The facilities will be operational on time as planned, but there will be some additional work to be done as suppliers can provide us with equipment. There have been significant delays in the availability of the LCD monitors for the monitor wall (and no readily-available alternatives can be found), so a temporary installation of CRT monitors is being provided to ensure the television control room is ready for use in Week 11 as planned. We are also still waiting for delivery of the correct desk mounts for LCDs in the radio studio and control room: the supplier has supplied us with incorrect items twice and we are trying to get them to deliver the correct mounts as ordered. In the meantime temporary mounts will be used until the correct ones are available.